PROJECT DEVELOPMENT - WORKPACKAGE LIST

Work-package No

Workpackage title

Lead
contractor No

Person-months

Start
month (*)

End
month

Deliverable
No

1

Overview of existing techniques

14

75

1

6

D1

2

Damage assessment

10

70

1

6

D2

3

Risk analysis

13

86

1

6

D3

4

Intervention strategies

8

75

4

9

D4

5

Innovative materials and techniques

6

55

1

12

D5

6

Reversible mixed technologies

9

68

1

15

D6-7

7

Experimental analysis

3

114

7

24

D8

8

Numerical analysis

5

112

7

30

D9

9

Calculation models

7

59

16

30

D10-11

10

Validation of innovative solutions and procedures

4

53

19

30

D12-13

11

Study cases

2

108

13

36

D14

12

Design guidelines

11

116

13

36

D15-16

1-M

Scientific coordination

1

46

1

36

D1-M

2-M

Administrative management

1

46

1

36

D2-M

3-M

Financial management

1

46

1

36

D3-M

 

TOTAL

 

1129

 

 

 


(*) Start date and end (delivery) date are referred to the beginning and to the end of indicated month, respectively. The starting date 0 (see Timetable, Table 7.4) is coincident with the beginning of the first month.
 NOTE: The number of person/months includes the contribution of permanent (non additional) staff members.